Hello, we got screwed by a contractor

Report
Question

Please briefly explain why you feel this question should be reported.

Report
Cancel

Hello, we got screwed by a contractor. He built a walk in shower, the shower pan he made does not pitch to the drain. What are my options?  He used a rubber sheet and some kind of concrete substance then our tiles.can it be saved without a total demo and rebuild. He took all our money.  I would try to do the repair myself.

Answer ( 1 )

  1. Please briefly explain why you feel this answer should be reported.

    Report
    Cancel

    So if I understand you right the shower pan is completed with the tiles?

    If so you can try to remove the tiles, extend the drain a little bit, add another layer of mortar and then the tiles. More than likely new tiles.

    Or yes rebuild the whole thing.