How long should it take to mud, sand/finish and paint a 2200 square foot house including the ceilings.

0 Shares
in progress 0
Rita Chandler 4 years 1 Answer 579 views

Answer ( 1 )

  1. That’s a big question. That would depend on how good your taper is. About 7 days for the most part.

    Day one – Tape

    Day two – second coat

    Day three – third coat

    Day four – sand. Maybe a extra for for touch ups

    Day five – Prime

    Day six – paint

     

    But could be up to two weeks. Really depends on the crew and weather.